4  Agile with iterations

Small teams do well with two-week iterations in GitHub Projects and a minimal ritual of planning and review. GitHub covers the essentials of Scrum and Kanban; what it lacks out of the box, such as burndown and velocity, isn’t missed with up to five people.

4.1 The concepts and where they live

Agile concept In Jira In GitHub
Backlog Backlog Table view sorted by priority
Sprint Sprint Iteration field (cycles generated automatically)
Story points Story points Number field “Estimate”
Epic → story → task Epic / Story / Sub-task Issue types + sub-issues with a progress bar
Sprint board Board Board view filtered by iteration:@current
Release Fix version Milestones
Roadmap Timeline Roadmap view
Reports Burndown, velocity Insights (burn-up and charts by field)
Automation Automation rules Built-in workflows + GitHub Actions

4.2 The iteration cycle

flowchart LR
    A["Planning<br/>(Monday, 30 min)"] --> B["Work<br/>(two weeks)"]
    B --> C["Review<br/>(last day, 30 min)"]
    C --> D["Retrospective<br/>(one improvement)"]
    D --> A

  1. Planning: state the iteration’s goal in one sentence (“the annual report exports to PDF”) and pull from the Backlog only what fits.
  2. Work: follow-up is asynchronous. Check the Board at the start of the day; with a collaborator, a short comment on the issue in progress is enough.
  3. Review: what got in, what didn’t, and why.
  4. Retrospective: one process improvement for the next iteration. One, not ten.

4.3 How to estimate

An estimate measures size and uncertainty, not hours. Use the 1, 2, 3, 5, 8 scale:

Points Means
1 Trivial, I know exactly what to do
2–3 Small, with few open questions
5 Medium, or with real uncertainty
8 Too big: split it into sub-issues before starting

After three or four iterations, the sum of points delivered per iteration gives a sense of capacity. Use it as a planning reference, never as a target.

4.4 Epics

An epic is a large body of work with a business goal. At Farol: “Import through the aggregator”, “Annual tax report”, “Inviting members to a space”. Each epic becomes an issue of type Epic, with its features and tasks as sub-issues. The epic’s progress bar shows how much is left.

4.5 Kanban or Scrum?

  • Alone: pure Kanban (continuous flow, no iterations) works well.
  • With a collaborator: iterations help agree on priorities and pace.
  • With customers or investors: iterations give you concrete dates to talk about.

4.6 When to move to Jira

GitHub stops being enough when one or more of these signs appear:

  • A team of more than five to eight people, with several boards that need to talk to each other.
  • A need for status workflows with rules (for example, “only QA moves to Done”).
  • Management asking for ready-made agile reports: burndown, velocity, cumulative flow.
  • Structured customer support with SLAs (that’s where Jira Service Management comes in).
TipIn this repository

The book is written in two-week iterations. Each iteration has a goal, such as “Part I complete”, visible in the Iteration field on the board.

NoteTry it

Write your next iteration’s goal in a sentence of no more than 15 words. If it doesn’t fit, the iteration is trying to do too much.